Dietmar Feichtinger Architectes

Dietmar Feichtinger Architectes

La Grenouillère Aquatic Center
Antony | 
France – 
2019

Client

Hauts de Seine Departmental Council

Start of construction

05 | 2023

Size

7 350 m²

Construction budget

76 M€

Competition winner

2019

Completion

05 | 2026


Located next to Parc de Sceaux, this project harmoniously integrates with a 9-meter elevation drop from north to south, blending with the natural topography. This aquatic center skillfully combines design elements for maintaining a small footprint to maximize expansive outdoor areas with distinctive landscaping. The architecture aligns with the land contours, embedding essential parts of the facility within the terrain’s elevation lines to reduce building volume and preserve the tranquil atmosphere.


Client: Hauts de Seine Departmental Council

Architect: Dietmar Feichtinger Architectes

General engineer: SETEC BATIMENT

Surface: 7 350 m²

Related Content

#246_Strasbourg_Piscine Kibitzenau_Main horizontal
#226_St. Gervais_Piscine_Main horizontal
#190_Paris_Stade_Ladoumegue_Main horizontal