2019

Client

Hauts de Seine Departmental Council

Start of construction

05 | 2023

Size

7 350 m²

Construction budget

76 M€

Competition winner

2019

Completion

05 | 2026


Located next to Parc de Sceaux, this project harmoniously integrates with a 9-meter elevation drop from north to south, blending with the natural topography.

This aquatic center skillfully combines design elements for maintaining a small footprint to maximize expansive outdoor areas with distinctive landscaping. The architecture aligns with the land contours, embedding essential parts of the facility within the terrain’s elevation lines to reduce building volume and preserve the tranquil atmosphere.


Team
Lead Architect: Dietmar Feichtinger Architectes
General engineer: SETEC BATIMENT
Landscape architect: VOGT Landscape
Hydrology engineering: SETEC HYDRATEC
Geotechnical engineering: TERRASOL
Commercial kitchen engineering: CONVERGENCE INGENIERIE
Acoustic engineering: TISSEYRE + ASSOCIES
ESSP consultant: CRONOS CONSEIL
BIM coordination & construction scheduling: OMEGA ALLIANCE
Cost consultant: Philippe COLAS

HQE – Sustainability
HQE approach | Biodiversity