White Night – Bridge the gap between the 28th and 29th of january 2006
Paris
28 01 2006
France

We are pleased to invite you to the installation on the night of 28th/29th January of the central part, the 106 metre long lentille – of the future Simone de Beauvoir footbridge across the Seine in Paris.

Tentative plan

23h30 Operation begins: river traffic is halted
23h30-02h30 The barge transporting the “lentille” moves to the middle of the river and is secured
02h30-05h00 Installation and adjustment of the lifting equipment
05h00-07h00 Lifting
07h00-10h00 Adjustment and fixing of the “lentille”

Related Content

Project

Nantes’ New Anne-de-Bretagne Bridge Prepares to Welcome Its First Visitors

Nantes
23 10 2026
France
Event

Finissage & Panel: Cities in Transformation – Sustainable Buildings and Infrastructure

New-York
17 09 2026
United States of America
Project

Opening of the school Paul Vaillant Couturier in Clichy-sous-Bois

Clichy-sous-Bois
15 09 2026
France
Project

Jules & Jim – A Historic Connection Reopened Across the Seine

Limay
11 09 2026
France